BACKGROUND
Inspire were awarded this contract via a competitive tender process with works due to commence in July 2019.
Throughout both schools a high proportion of internal walls had not been taken up to the underside of the roof deck and provided no form of compartmentation. In addition to this a number of services and cabling had been installed through compartment lines and had not been fire stopped correctly.
THE WORKS
The following materials were used:
- Stopseal Batt ablative coated stonewool board.
- PyroPro HPE sealant water based acrylic sealant.
- Pyrocoustic sealant water based acrylic sealant.
- PipeBloc EL wrap penetration sealer.
THE RESULT
Our works included a full survey of both schools and the scheduling of works required and the installation of certified fire stopping/compartmentation. Works were completed within 5 weeks on time and to budget.
Upon completion of the project a full schedule documenting works completed were provided with all works certified.